5/14/99 |
All trusses are up and they are
being braced and sheathed. |
![](office13.jpg)
|
5/20/99 |
Wall sheathing proceeding. Columns
being sized & formed. Plumbing and HVAC ducts
being installed.
|
![](office12.jpg) |
5/28/99
|
EMT & ENT installed in office.
Aluminum
Frames for Windows installed.
|
![](office13b.jpg)
|
6/01/99 |
All Concrete completed. Roadbase graded and
blacktop applied.
All beams and
posts up in shop.
|
![](Shop05.jpg)
|
6/14/99 |
All exterior windows installed. Stucco paper & lath
mesh & lath wire applied.
|
![](office14.jpg) |
6/15/99 |
Steel walls and roofs beginning to
go up. Roof
& all walls are insulated.
Wire & conduit
for shop lights being mounted.
|
![](Shop07.jpg) |