4/26/99 |
Our resident "gopher."
More red iron up
and massive footings for the office columns are being
poured.
|
![](Shop04.jpg) |
4/28/99
|
Office - all footings poured &
curing.
Shop
- most large posts and beams are up.
|
![](office07.jpg)
|
5/03/99
|
More purlins up and side posts
& beams up.
|
![](office08.jpg)
|
5/04/99
|
All office columns mounted on their
footings.
|
![](office09.jpg)
|
5/05/99
|
Beams mounted to columns.
|
![](office10.jpg)
|
5/10/99 |
Truck dock proceeding, Office roof
trusses going up. |
![](office11.jpg) |